TIMELINE

Task
Completion Date
EngineeringJanuary 2024 - July 2024
Bidding PhaseAugust 2024
Sidewalk StartApril 2025
Sidewalk CompletionSeptember 2025
Valley View Construction StartApril 2025
Underground InfrastructureJune - September
Road ConstructionSeptember - October
Project CloseoutDecember 2025


Construction Drone Footage - March


FUNDING



The funding for this infrastructure comes from the Northeast NIA which is a local authority designed to promote development within City's. The project estimates for the infrastructure to support Valley View #1 are $1,200,000.

communications

The City strives to communicate with residents and property owners effectively. A summary of communication issued related to Valley View Development is listed below. To receive direct updates via email and text please create an account and sign up for Notify Me construction updates.

DateCommunication
January 3, 2025Notify Me - Construction Contract Awarded by City Council
January 15, 2025Letter to Residents - Valley View Phase 1 and Neighborhood Construction Project
February 21, 2025Notify Me - Valley View Construction Project -Tree Clearing
April 11, 2025Notify Me - Valley View Construction Update
April 17, 2025Letter to Residents - Upcoming Sidewalk Construction
April 23, 2025Notify Me - Allen Road and Forest Street Sidewalk Project
April 28, 2025Notify Me - Forest Street and Allen Road Sidewalk Project Update

May 9, 2025Notify Me -  Neighborhood Community Meetings


May 14, 2025Letter to Residents - Neighborhood Community Meetings
July 3, 2025Notify Me- Valley View Construction Update
July 25, 2025Notify Me- Valley View Construction Update
September 25, 2025Notify Me- Valley View Construction Update
October 14, 2025Notify Me- Valley View Construction Update
October 17, 2025Notify Me - Valley View Construction Update- Allen Road Mill and Pave
October 23, 2025Notify Me - Valley View Construction Update- Allen Road Paving
October 24, 2025Notify Me- Valley View Construction Update-
Allen Road Paving Postponed

Valley View Site Condominium plan

The following documents have been submitted by the Developer for review for the Planning Commission as part of the Site Condominium approval process.

 Valley View Updated Plans

Site Condo Application Package

Valley View Master Deed

Valley View- Exhibit A to Master Deed