Sign up for Construction Notifications on Green Street, Jefferson Street, and Activation Zone Improvements.
SCOPE
The City will be completing reconstruction West Green Street between Eagle Street and Jefferson Street as part of the first improvements to the Activation Zone area.
TIMELINE
Task | Completion Date |
Engineering | Fall 2021, 2022, 2023 |
Bidding | May 25, 2023 |
Utility Relocating | August 14, 2023 - September 15, 2023 |
Construction - Mobilize for Street Reconstruction | September 5, 2023 |
Construction - Closure of W Green Street between Eagle and Jefferson | September 5, 2023 |
Construction - Demolition | Week of September 5, 2023 |
Construction - Sidewalk and Curb Installation - North Side | September 11 - September 22, 2023 |
Construction - Street Resurfacing | TBD |
Construction - Substantial Completion | TBD |
Project Closeout | TBD |
FUNDING
The City of Marshall was awarded a Michigan Economic Development Corporation (MEDC) Revitalization and Placemaking Grant (RAP) for this project. The grant required matching funds which are being provided by the Downtown Development Authority, the Local Street Millage Fund, and a grant from the Cronin Foundation. The project budget is $1.3 million with half covered by the RAP grant and half providing in matching funds by the City. The Green Street Reconstruction portion of the project, planned for 2023, is estimated at $610,000.