project map
scope
The City is completing watermain replacement and street reconstruction on E Prospect from N Liberty St to East Drive. The construction will start with milling of the street and watermain installation within the road. Some sidewalk improvements and installations will also be completed.
timeline
Task | Completion Date |
Engineering | January 2022 |
Bidding | January 24, 2023 |
Mobilize | June 12, 2023 |
Construction - Mill Street | June 14, 2023 |
Construction - Watermain Installation | June 22, 2023 - Estimated July 14, 2023 |
Construction - Street Installation | Final Paving - August 18, 2023 |
Substantial Complete | Scheduled August 15, 2023 |
Project Closeout | September 15, 2023 |
funding
The City is funding this project through three funds including the Water Fund, Local Street Fund, and Street Millage Fund. The Water Department is funding this work through the 2022 Revenue Bond Sale and Fund Balance.