Leggitt Road Reconstruction

project map

red line over leggitt road

Sign Up for Construction Notifications for Leggitt Road Reconstruction

scope

The Leggitt Road reconstruction project will include new watermain, sanitary sewer, stormwater management, and a complete new road surface. 

timeline

TaskCompletion Date
EngineeringNovember 2022
BiddingJanuary 25, 2023
MobilizeMay 3, 2023
Construction - Mill Leggitt Road Asphalt SurfaceCOMPLETE
Construction - S Kalamazoo Ave Intersection ClosedCOMPLETE
Construction - Watermain InstallationCOMPLETE
Construction - Sanitary Sewer Installation
May 18, 2023 - June 9, 2023
Construction - S Kalamazoo Ave Intersection ClosedEstimated week of June 12, 2023
Construction - Stormwater Management ConstructionMay 22, 2023 - June 16, 2023
Construction - Street SurfacingEstimated week of June 12, 2023


funding

This project is funded through several City funds including the Water Fund, Wastewater Fund, Local Streets Fund, and the Street Millage Fund. The total project is estimated at $715,000.