Find Updates on the Michigan Avenue Construction Project

7/12/19

Michigan Ave Water Main Replacement:

Progress has begun on the installation of the water main in phase 2.  The contractor has placed the main between Grand Street and Eagle Street and will begin testing of this main this weekend.  Due to logistics for Consumers Energy with the re-routing of some internal building gas lines we are unable to place the main between Eagle Street and Jefferson Street until later this month.  The contractor will begin removals of concrete for installation of the electrical conduits and other miscellaneous work. 

 

 

The weekend of July 19th, 20th and 21st, Michigan Ave. at Eagle St. will be closed for installation of a water main crossing.  This closure may begin Friday July 19th at 4:00 pm with the road opened back to traffic by the end of the day Sunday July 21st.  It is not planned that any businesses will be without water during this time unless issues arise during the construction.

Tentative overall schedule for water main project:
• April 29, 2019 - Phase 1 work will start.
Marshall Ave to Jefferson St – North Side. Work will progress from Marshall Ave working westerly.
• Mid May – Sidewalk will be removed and water service installations will begin for Phase 1.
• Early June – Phase 1 water main will be completed
• Mid-June – Phase 2 – Traffic control will be set-up and work will begin 
Phase 2 – Brooks Fountain to Jefferson Ave. - South Side. Work will progress from the Fountain easterly.
• Early July – Sidewalk will be removed and water service installations will begin for Phase 2.
• Late July/Early Aug (Date TBD) – Phase 3 will start (Weekend Michigan Ave Street Closure @ Eagle Street)
Eagle Street intersection – Friday to Sunday complete Michigan Ave closure with detours.
• Completion Mid- August
• The contractor is aware of the following events and we will be accommodating these during the construction per their contract. These include the May 18 – Hospitality Classic, May 27 – Memorial Day Parade, June 22 – Blue’s Fest and July 4 – Chicken BBQ.

Things to know:
• No on-street parking will be allowed, within the construction areas, during each phase of the project. Please direct patrons to the public lots behind the buildings. Signs will be erected within the construction zone directing people to these public parking lots throughout the project.
• Water outages will be minimized as best we can. 
• When services are tied over into the new water main, individual businesses will experience a water outage of approximately one hour long. 
• We will either be hanging door tags or making personal contact prior to these outages to assist with scheduling as best we can. Being aware of where the contractor is working will help you to anticipate the timing of your individual service installation.
• The city has hired Stantec Consulting to assist us in field management of the project. Marc Hubbel with Stantec, will be on-site throughout the project and assist in notifications during the project. Additionally folks are welcome to contact the city at 269-781-5183 or the Engineering Department at 269-558-0323.
• If there are issues that occur that need to be addressed please contact city staff to work through the issue rather than talking with the contractor and their employees as they don’t always have the resources to deal with certain situations.
• Please keep in mind that construction schedules can be impacted by weather and other unanticipated issues that can create schedule delays. The City and our contractor are well aware of the frustrations that exist around construction project such as this and we will do our very best to communicate as efficiently as we can and try to minimize these disruptions.

 

 

 

 Please visit our facebook page for the most up to date information:

Marshall MI Michigan Ave Construction 2019

 


posted 07-12-2019 [Engineering]